MAR 2 Civil Earthworks

June- July 2018

Roy Hill
RH Mine, 100kms North of Newman
June- July 2018

We were awarded this scope of work within our three year mine services contract. Our scope of work included the construction of gravel access roads and drill pads in support of the expanding resource definition works for the mine..

The works included 52 hectares of clearing and stripping, 35000 m³ of gravel production, 17kms of road construction and the construction of 36 drill pads.

Equipment utilised included 30t excavators, D9 dozer, 740 articulated trucks, 16H grader, flat drum roller and water carts.