Mt Magnet Stage 9 TSF 3 Raise

August to November 2019

Ramelius Resources
Leonora
August to November 2019

IMC was contracted to underway a TSF raise over a four month period prior to Christmas. The scope of work included foundation preparation, load and haul embankment fill from waste dumps, moisture condition place and compact fill materials, placement of rock protection to outer embankment and raising decant structure.

The raise utilised equipment including 349DL and 320 excavators, 740 articulated trucks, D8T dozers, 14M graders, L70 loader, rollers and 740 articulated watercarts.