Thunderbox TSF Raise

February 2019 - ONGOING

Saracen Minerals
Leinster, 370km North of Kalgoorlie
February 2019 - ONGOING
5 Months

Another IMC project secured through successful works carried out in the Goldfields region at the end of 2018. The two year,scope of work includes multiple upstream raises utilising the existing tailings to raise the perimeter embankments of the tailings facility. Our scope includes foundation preparation, load & haul, condition and compact tailings, raising decant access ways with rock, raising the decant structure and load haul and place rock to outer embankments.

Throughout this project plant includes 633 scrapers, D8T dozer, 14M Grader, articulated dump trucks and watercarts, 30T excavators, 18T rollers.

The project is being completed on time, incident free and on budget.