The company was contracted to undertake a rolling culvert installation package across major mine access roads for FMG’s Cloud Break Mine, given our close proximity of other works within the region.
Our work included excavation, sub base preparation,600-1500mm multi culvert installations, select material fill and compact and base course construction.
Equipment utilised included 336DL excavators, IT62H handlers, 140M Graders, articulated dump trucks, watercarts, rollers and compactors.
The project was completed on time, incident free and on budget.