The scope of work at Deflector includes:
- construction of a new 2-cell tailings storage facility including clearing of vegetation
 - topsoil stripping
 - foundation preparation
 - load and haul of embankment fill from waste dumps
 - moisture condition place
 - compact clay fill materials
 - installation of new decant structures and HDPE liner
 
The project utilises the following equipment: dozers,
excavators, scraper, articulated dump trucks, road-trains,
graders, loaders, rollers and articulated watercarts.