Kathleen Valley

December 2022 – Ongoing

Liontown Resources
Kathleen Valley Lithium Mine Site, Leinster
December 2022 – Ongoing

Kathleen Valley is a new Lithium project for Liontown Resources Limited. The site is located 60 km north of Leinster in the Northern Goldfields.

Iron Mine Contracting have secured a long-term open pit mining contract. The contract consists of 3 mining fleets and includes the drill, blast along with load & haul components.

11.8 million BCM will be mined with a peak workforce of 180 people. A new 580 room camp is under construction along with a 4 million tonne per annum processing plant.

In addition, IMC will be completing the construction of the TSF including the bulk earthworks, HDPE liner and finger drains. Mobilisation to site commenced in December 2022 and the project has been fully operational since February 2023.