King of the Hill TSF5

May 2022 - February 2023

Greenstone Resources (WA) Pty Ltd
King of the Hill Mine Site, Leonora WA
May 2022 - February 2023

Red 5’s King of the Hills Operation is located northwest of Leonora in the Goldfields region of Western Australia. TSF 5 is a new facility located to the east of the process facility.

During the construction of TSF 5 IMC undertook the following activities

  • Cleaning of 93 ha of vegetation
  • Stripping and haulage to stockpile of 94,000 m3 of topsoil
  • 805,000 m3 of new embankments, decant causeway and clay liner construction
  • 265,000 m2 of HDPE liner
  • Toe drain and underdrainage construction

IMC self-performed the bulk earthworks, civil works and underdrainage installation of the project and managed the supply and installation of the HDPE liner by a specialist subcontractor. The workforce on the TSF 5 project peaked at 60 personnel and there were zero LTI’s and no environmental incidents on the project.