Mt Holland TSF

June 2022- ongoing

Gold Fields Limited
Laverton, WA
June 2022- ongoing

Construction of new TSF including clearing and grubbing, topsoil and subsoil stripping, 410,000m3 of perimeter embankment and decant accessway construction, supply and install a 2km water pipeline and construction of HDPE lined water storage pond, construction of downstream seepage interception system and supply and installation of monitoring instrumentation. Additional works onsite included construction of new roads and upgrading of existing roads, clearing, topsoil stripping and subsoil stripping of new waste dumps, screening rock basecourse and trimming of ROM.