Roy Hill Ultrafines

August- December 2018

Roy Hill
RH Mine, 100kms North of Newman
August- December 2018

We were awarded this project, encompassing the civil earthworks for the downstream iron ore processing plant. These works were carried out amongst an operating processing plant, with particular focus on limited area disturbance during iron ore operations.

The work included clearing and bulk earthworks, construction of roads and installation of drainage culverts, decommissioning of power lines and the relocation and installation of sewerage spray fields.

During this project the equipment utilised included D8T dozer, 140M grader, 40t articulated dump trucks and watercart, 8 wheel watercart, 30T and 20T excavators, vibrating rollers, bobcats, 980 FEL’s and triple road train side tippers.