Waste Dump Rehabilitation

December 2014 to March 2015

FMG
Cloud Break, 110km NW of Newman
December 2014 to March 2015

The company undertook rehabilitation of the Cocos, Green and Brampton waste dumps at FMG’s Cloud Break mine, totalling 109ha of waste dump works.

Our scope of works included the full project management of the land form profiling, down drains, rock armour, retention basins and top soil placement and ripping over a four month period, during the wet season to meet client constraints.

The equipment included D10-9 Dozers, 980 FELs, 740 Articulated dump trucks, 30t excavators, 14M Graders, Screening plants, stackers, water and service equipment.